Facade Restoration: A Guide for Building Owners

Most facade restoration projects start with something small. A piece of coping lands on the pavement, a crack opens above a window, or a leaseholder reports damp on an inside wall that nobody can explain. By the time an owner picks up the phone, the question is rarely whether work is needed. It is how much, how soon, and what it will cost to find out.

A facade does three jobs at once. It keeps weather out, it carries load, and on many buildings it plays a part in fire performance. Restoration means putting those three back in order without stripping the building of the character that made it worth keeping. This guide covers what the work involves, the defects behind most schemes, the consents owners forget, and the checks worth making before anyone puts up scaffolding.

The term stretches a long way. At one end it means repointing and localised brick replacement on a Victorian terrace. At the other it means stripping and rebuilding a failed external wall on a residential block, with structural alterations behind it.

Most schemes sit somewhere between the two: repointing in a mortar that matches the original, cutting out and replacing spalled brick or stone, stone indents and mortar repairs, cleaning, render repair or recovering, replacing cills, copings and parapets, renewing sealant and movement joints, repairing rainwater goods, redecorating joinery, and reinstating the ironwork that carries balconies and railings.

What separates a restoration from a repair is scope and sequence. Repairs chase defects one at a time. A restoration takes the whole elevation, works out why it is failing, and fixes the cause while the access is up. Access is usually the single most expensive item on the job, so the economics push hard towards doing everything at once.

Six causes account for most of the facade work we see in London and the South East.

  • Failed pointing — mortar is sacrificial and meant to be. The trouble starts when a soft lime-bonded wall is repointed in hard cement. Water that used to evaporate through the joint now evaporates through the brick face instead, and the brick spalls. A good proportion of what looks like brick failure is mortar failure from forty years ago.
  • Cavity wall tie corrosion — steel ties rust, and rust expands. The outer leaf lifts in horizontal cracks at regular courses, roughly every sixth or ninth depending on the original spacing. Left alone, the outer leaf loses its restraint.
  • Corroding embedded steel — early twentieth-century buildings with steel frames behind stone or brick suffer as the steel corrodes and expands, cracking the masonry in front of it. Known in the trade as Regent Street disease. It is slow, expensive to fix properly, and it does not stop on its own.
  • Render failure — cracking, debonding and hollow areas, usually where cement render has been applied over a substrate that moves, or where water has found a way behind it through a defective cill or coping.
  • Movement — settlement, thermal movement with no joints to accommodate it, or a bay that was never properly tied in. Cracks that are stepped, tapered and seasonal tell a different story to cracks that are straight, uniform and getting wider. Our guide to structural works covers how to read them.
  • Water in the wrong place — blocked or split rainwater goods, failed parapet flashings, open joints at copings and cills. The damp that shows up inside the building is often metres away from the thing that caused it.

Cladding and external wall systems sit alongside all of this and follow a different route, driven by fire safety rather than weathertightness. Where a building has a cladding system and residential units, that assessment comes first and shapes everything else.

The most common mistake in facade work is pricing a scheme from a visual inspection taken at ground level. Binoculars find the obvious. They miss hollow render, loose pointing, failed ties and the condition of the backing masonry entirely.

A proper facade condition survey means close inspection of the elevations, by mast climber, mobile elevating work platform, rope access or a scaffold erected for the purpose. It should include opening up at agreed locations, mortar analysis where the building is historic, and tie testing where the construction warrants it. Rope access is usually the cheapest way to inspect a tall elevation, and the cost is trivial next to a contract sum built on guesswork.

What the survey produces is an elevation-by-elevation schedule with quantities. That schedule is what gets priced. Without it, every tender describes a different scheme and the comparison means nothing.

Facade work touches more regulatory regimes than almost any other kind of building work, and the permissions sit with different bodies on different timescales.

  • Listed building consent — required for work affecting the character of a listed building, inside and out. Repointing a listed facade in the wrong mortar is an offence, not a snagging item. Conservation area status brings its own controls, and some authorities add Article 4 directions that remove permitted development rights.
  • Highway licences — scaffolding, hoardings and gantries over the public highway need a licence from the highway authority. They carry conditions and they take time. On a busy street the licence can govern the programme more tightly than the works do.
  • Party wall notices — required under the Party Wall etc. Act 1996 where work affects a party structure or involves excavation near a neighbour. Notice periods run to one or two months depending on the section.
  • Section 20 consultation — on a leasehold residential building, where any single leaseholder contributes more than £250, the landlord must consult under section 20 of the Landlord and Tenant Act 1985. That is two stages of notice at a minimum of 30 days each, plus a notice of reasons where the cheapest estimate is not the one accepted. Skip it and recovery is capped at £250 per leaseholder however much the works cost, which on a facade scheme is a six-figure gap.
  • Building control and the Building Safety Regulator — work to a higher-risk building, meaning at least 18 metres or seven storeys with two or more residential units, goes through the Building Safety Regulator rather than a local authority or approved inspector. The approval stage adds months that have to be planned for, and sits alongside the wider building safety regulation changes now in force.
  • CDM 2015 — applies throughout. Facade work is work at height on an occupied building with a public interface, and the duties it places on the client are real ones.
  1. Has anyone diagnosed the cause, or only described the symptom? A schedule that says “repoint defective areas” without saying why they are defective will produce the same defect again in fifteen years.
  2. Is the scope based on measured quantities? Provisional sums are where facade budgets go to die. Reduce them to the areas genuinely unknowable until access is up.
  3. Who carries the opening-up risk? Agree before tender what happens when the backing masonry is worse than the survey suggested, and how it gets valued.
  4. Is the access strategy priced and licensed? Access can be a third of the cost. It also drives the programme, the neighbour relations and the licence conditions.
  5. Have the consents been started? Listed building consent, highway licences and section 20 each run on their own clock, and none of them can be compressed at the end.
  6. Does the specification name the materials? Mortar mix, sand source, brick match, stone bed and finish. “To match existing” is an argument waiting to happen.

Four failures account for most of the facade disputes we are asked to look at. The survey was done from the ground, so the contract sum was wrong before anyone signed it. The access went up before the consents were in, and the scaffold stood idle on a licence that cost money every week. Nobody specified the mortar, so the contractor used what was to hand, and the repointing now reads as a stripe across the elevation. Or the section 20 consultation was treated as paperwork to catch up on later, and the landlord finished the job unable to recover the cost.

None of those are construction problems. They are decisions taken before the work started, by people who had not been told what the decision would cost.

Q10 Consulting works on facade restoration across London and the South East as Principal Contractor, Contract Administrator and Quantity Surveyor, under the JCT form that suits the procurement route. That means commissioning the right survey before anything is specified, turning it into a schedule that can actually be priced, handling the consents on their own timescales, and running the work once it starts.

If you have a facade with cracking, spalling or water getting in, and quotes that vary more than they should, the usual reason is that each contractor has priced a different scheme. The fix is a measured schedule everybody prices against, and it is worth having before the tenders go out.