Most of the construction disputes we are asked to unpick did not begin with bad building. They began with the wrong JCT contract, or the right one used badly. The form you sign decides who carries the design risk, how long the employer has to answer a delay claim, and what happens to the money if the job stops. This guide covers the main JCT contract families, what actually changed in the 2024 editions, and the five checks worth making before anyone signs.
A JCT contract is a standard form published by the Joint Contracts Tribunal and used on a large share of UK building projects. Its job is to allocate risk before anything goes wrong: who designs what, who carries the cost of the unexpected, how variations are valued, when payment falls due, and what either party can do if the other fails to perform.
Standard forms matter because the alternative is bespoke drafting nobody has tested. A JCT contract carries decades of case law behind it, and an estimator, a quantity surveyor and a solicitor will all read the same clause the same way. That removes a layer of argument before it starts.

There are more forms than most clients need to know about. In residential and mixed-use work, four cover almost everything:
Beyond those sit Construction Management, Management Building, Measured Term, Framework and the Homeowner forms, each built for a particular procurement route. Choosing between them comes down to two questions: how much design is the contractor taking on, and how much price certainty does the employer need before work starts.
JCT began rolling out the 2024 Edition with the Design and Build family on 17 April 2024, followed by the Standard Building Contract, Intermediate and Minor Works families through the rest of the year. The Complete Edition was announced in December 2024, with the remaining families published across 2025. The changes below are those in the Design and Build 2024 form; the other families differ in places.
The building safety drafting is the part worth watching. It handles Building Regulations notices and fees competently enough, but it does not address dutyholder declarations outside higher-risk buildings, and it merges the CDM and Building Regulations principal contractor and principal designer roles into one clause. On any project touching the Building Safety Act, expect amendments rather than relying on the published form.

Four failures account for most of what we see. A letter of intent intended to cover enabling works quietly runs the whole job, so there is no executed contract when the dispute arrives. Instructions are given verbally and confirmed later, or not at all. Certificates slip past their dates, which hands the contractor an argument on payment. And nobody reads the amendments until it matters, by which point the risk has already moved.
None of these are drafting problems. They are administration problems, and they are avoidable with someone named and accountable for running the contract from the start.

Q10 Consulting acts as Employer's Agent, Contract Administrator and Quantity Surveyor on residential and mixed-use projects across London. That means advising on which JCT contract suits the procurement route before anything is signed, then running it properly once it is: valuing variations, certifying payment on time, and dealing with delay claims on the evidence rather than on the exchange of letters.
If you are weighing up a procurement route, or you have a contract in front of you that does not look right for the job, it is worth a conversation before signature rather than after.