Building Safety Regulations: 7 Changes for 2026 and 2027

Building safety regulations in England are going through their biggest period of change since the Building Safety Act came into force. The autumn of 2026 alone brings a second staircase requirement for tall residential buildings and a new levy on residential development. Behind those sit a regulator that has been rebuilt, an approvals process that is finally speeding up, new energy standards and plans for a single construction regulator. This guide sets out the seven changes that matter most, when each one takes effect, and what they mean if you are commissioning, designing or building over the next two years.

Seven changes to building safety regulations matter most. Some are already in force, some land within days, and some are still working their way through Parliament.

  • 27 January 2026 — the Building Safety Regulator became a standalone body
  • Through 2026 — Gateway 2 decisions on higher-risk buildings speed up
  • 6 April 2026 — residential evacuation plans became mandatory in many blocks of flats
  • 30 September 2026 — second staircases required in new residential buildings over 18 metres
  • 1 October 2026 — the Building Safety Levy applies to new residential schemes
  • 24 March 2027 — the Future Homes Standard comes into force
  • Still to come — a single construction regulator and reformed building control

On 27 January 2026 the Building Safety Regulator left the Health and Safety Executive and became an independent public body sponsored by the Ministry of Housing, Communities and Local Government. The move followed a difficult 2025 in which approval delays held up hundreds of projects, and it is the first practical step towards the single construction regulator recommended by the Grenfell Tower Inquiry.

For anyone working under building safety regulations, the change of structure matters less than the change of focus. The regulator now deals only with buildings, and its stated priorities include more site inspections and tackling the national shortage of building inspectors. Expect closer scrutiny of competence and records, not less.

Gateway 2 is where building safety regulations bite hardest on a programme.

Higher-risk buildings — those at least 18 metres or seven storeys with two or more homes, plus hospitals and care homes of that height during design and construction — cannot start on site until the regulator has approved the building control application at Gateway 2. In the summer of 2025, fewer than four in ten new-build applications were being approved and the median wait was 43 weeks.

The picture a year on is far better. In the regulator’s data for summer 2026, more than nine in ten decisions on new higher-risk buildings were approvals, and the median time had fallen to around 22 weeks. The target is 18 weeks for non-complex applications by March 2027. The latest Gateway 2 figures are published on GOV.UK.

Two points are easy to miss. First, refurbishment inside an existing higher-risk building goes through the same gateway, and those decisions have been taking longer than new build. Second, the quality of the application is now the main factor within your control — incomplete or inconsistent submissions remain the most common reason for delay.

From 30 September 2026, amended Approved Document B requires two protected staircases in any new residential building where the top storey is 18 metres or more above ground level, alongside revised guidance on evacuation lifts, protected lobbies and minimum stair widths.

External escape staircase providing a second means of escape from a block of flats

Schemes that made a building control application before that date can keep the previous rules, but only if the work is sufficiently progressed within 18 months — in practice, foundations poured or piling started by 30 March 2028. A scheme that stalls on site loses that protection and needs a fresh application under the new rules. Existing buildings are unaffected. The government announcement sets out the background.

The levy is a charge rather than a technical standard, but it is collected through the same building control process as the rest of the building safety regulations.

From 1 October 2026, building control applications for new residential developments of at least ten homes, or 30 bedspaces of purpose-built student accommodation, attract the Building Safety Levy. It is charged per square metre of new residential floorspace at rates set for each local authority area, with a 50% reduction on previously developed land. The government expects it to raise around £3.4 billion over ten years to fund the remediation of unsafe existing buildings.

Applications made before 1 October fall outside the levy. Non-profit registered providers of social housing are exempt, and refurbishment that creates no new homes is not caught — but conversions and extensions that add ten or more dwellings are. Crucially, a completion certificate will not be issued until the levy is paid. The government has also consulted on raising the threshold for smaller schemes, so check the current position before appraising a site.

This is where building safety regulations meet day-to-day building management.

Since 6 April 2026, the responsible person for high-rise and certain medium-rise blocks of flats must offer personal emergency evacuation plans to residents who may need help leaving the building in a fire, and keep building-level evacuation information up to date.

Fire doors, emergency exit sign and alarm panel on a communal escape route

For contractors working in occupied buildings this adds a practical duty. Any works affecting escape routes, lifts or fire doors need planning around those evacuation arrangements from the outset, rather than being discovered part-way through the programme.

The Future Homes Standard sits outside the building safety regulations proper — it is an energy change — but it revises the same Building Regulations and lands on the same schemes. Published on 24 March 2026, it comes into force on 24 March 2027, or 24 September 2027 for higher-risk buildings. New homes will need low-carbon heating such as heat pumps, rooftop solar where practical, and improved fabric performance, with the aim of cutting carbon emissions by around 75% against 2013 standards.

Homes with a building control application in before 24 March 2027 can be built to the current Part L, provided work starts before 24 March 2028. After that date everything must meet the new standard.

This is the next phase of building safety regulations reform, and the one with the longest lead time.

In July 2026 the government confirmed it will create a single construction regulator, built on the Building Safety Regulator and covering buildings, the professionals who work on them and construction products. It needs primary legislation, so this is a change measured in years rather than months. The government response to the consultation sets out the plan.

Alongside it, an independent panel has recommended a single statutory building control system in which work is allocated to inspectors by risk and competence rather than chosen by the client. The government has accepted the principles and is developing a digital roadmap for building control. The direction of travel across all of these building safety regulations is consistent: more weight on competence, and more weight on accurate, accessible information about every building.

Scaffolding to the facade of a building undergoing refurbishment works
  • Establish early whether the building is higher-risk, and build a realistic Gateway 2 period into the programme
  • For residential schemes near 18 metres, confirm which staircase rules apply and track the 18-month transition date
  • For schemes of ten or more homes, model the levy in the appraisal and deal with it in the contract
  • Programme the Part L transition alongside the building control application, not after it
  • Treat records as part of the build — the golden thread of information is scrutinised at every gateway

None of these changes is unmanageable on its own. What catches projects out is the combination — a scheme that now needs a second staircase, pays the levy, waits for Gateway 2 and has to meet a new Part L, all on the same appraisal. The earlier those questions are asked, the cheaper they are to answer.

Q10 Consulting works with building owners, developers and housing providers from feasibility and procurement through to delivery as main contractor, including refurbishment in occupied buildings. If you have a project affected by these building safety regulations and want a second opinion, get in touch for an initial conversation.